Monday, November 15, 2010

Pot Belly Pigs For Sale Ga

Es ist super viel passiert...

... in this one week. Unfortunately I had not the time to complete the blog!
As incorporated in the plan last Wednesday, the stairs - she looks great and we are subsequently glad that the first selected marble white throughout was not available. Friday we went on with the plumbing installation - so the toilets were installed and prepared the heating. The storm of last Thursday, unfortunately, has caused the first injury. When I came to the site on Friday morning, he hung our 3-blinds like a flag in the wind. He had torn out of the rail and flew merrily to himself. The damage has been repaired once coarse and the mechanics have taken him at least back into the rail. However, some slats and the rails are bent. This will soon be repaired. Saturday morning came and our roll-up door for the garage. Now we can put some things already :o)))). Samstag/Sonntag haben Andreas und ich dann unsere Waschtische vormontiert, einige weitere Baumarkt-Gänge absolviert und zum Teil auch schon eingebaut.
Unsere Pflasterer waren auch schon fleissig. So ist die Garagenauffahrt für die Pflasterung ausgehoben und ein Eingangspodest vorbereitet. Die Steine liegen schon alle auf dem Grundstück und morgen geht es dann mit der Pflasterung weiter. Heute war es nun soweit...gegen 16.00 Uhr wurde unsere Heizung gestartet. In den oberen Räumen - die mit den Heizkörpern werden nun langsam warm. Unter mit der Fußbodenheizung konnte ich es noch nicht merken - allerdings dauert es auch eine ganze Zeit, da diese ja nur langsam hochgefahren werden darf. Unser Maler hat heute auch angefangen - er streicht the time the room with undercoat. Office, bedroom and hallway are up already done. Oh dear ... quite a lot - I hope not too confusing: o))) - am frozen through and go straight to the couch! But here are a few pics:


The new roll-up door!
The initial pedestal
The basin is formed with mounting - missing only the two drawers
The stair handrail finished!

My first excavator ride o)






Tuesday, November 9, 2010

Columbus, Oh Male Brazilian Wax

Entwässerung ist fertiggestellt!

The house is now nothing happens, but Güner has completed the drainage . Tomorrow is supposed to come up the stairs - I am curious. We shall first line with paper so that it is not immediately scratched from all the sand that we are still dragging into the house. Yesterday, yes the kitchen farmer was there ... I have was

The kitchen, drawn as it: you picked out a few pictures of our planned kitchen.
this picture I once copied from hackers. We get
the Classic mat in front of Capri magonlia. But what we get in the drawing
other attacks - very important!
Our highlight - with crushed ice for caipirinhas o)
The refrigerator is on the right side of the wall between the window and
of 2 element to the terrace


... and the hood! She sits between the two
light soils.

Monday, November 8, 2010

Blazedtv Numero De Serie

Die Außenarbeiten beginnen und neue Termine!

have now begun the field work. Guner's team digging at the time strongly on the property, to lay the drainage. Many dates I could then just with Mr. Holtermann, our construction manager to discuss the spot: The plumbing and heating trade comes on Thursday and Friday and installed the toilets, the heating is slow and high (important because we have indeed in the entire EC-floor heating). Our stairs are installed on Wednesday and the garage on Saturday. A date now chasing the next kitchen studio Kassens - Mr. Kassens - was just on the ground and has once again measured the kitchen and checked the connections ... everything ok ... the kitchen can get. This is for 16-17. December intended to be installed! On the weekend of 18/19. December starts then our move * happy *. And so seeing the beginnings our Buddelei of:


"Bodo" \u200b\u200b/ Güner with the excavator!
to a good start!

Sunday, November 7, 2010

What Is Cervical Mucus Like Am

Die Außenfugen sind fertig!

On Wednesday our field joints were completed. Are still wet at the moment, but now - three days later they will have brighter. This weekend we have a lot done! The kitchen is decked over, above, all areas of the concrete and sheet remains free und es ist gefegt. Der Badezimmerwaschtisch ist vormontiert und wartet auf den Anbau. Sogar der Briefkasten ist schon angebaut. Puuuhhh...wir waren ganz schön durchgefroren - kein Wunder bei 4 °C. Morgen nachmittag kommt Fa. Kassens, um unsere richtige Küche auszumessen. Abends treffen wir uns noch mit unserem Maler, der dann ja am Samstag loslegt. Ihr seht, es geht mit großen Schritten voran. Hier noch ein paar Bilder:

Die Außenfuge ;o)

from the side!


The vanity base cabinet (1.20 m wide)


Our mailbox!